Saturday 18 May 2013

Weatherboard, Brickwork, Eaves and Insulation

The brickwork started on 10/05/2013, some of the cladding, eaves and insulation was installed during the week starting 13/05/2013.

WP_20130510_003(1)

James Hardie Scyon Linea weatherboard being installed.

 WP_20130510_005(1)

WP_20130510_011(1)

WP_20130510_014(1)

Linea around dining room stacker door.

WP_20130515_004

Alfresco ceiling and eaves.

WP_20130516_001

WP_20130516_002

Eaves around the skillion roof.

WP_20130516_003

Eaves.

WP_20130516_005

WP_20130516_007

Wall insulation was installed on 17/05/2013. Dining and family.

WP_20130517_001

Media

WP_20130517_002

More linea on 17/05/2013. Alfresco area.

WP_20130517_003

Have to love the weather in Queensland.

WP_20130517_005

WP_20130517_007

We went to the outdoor living and landscape expo on 18/05/2013 to get some ideas for finishing the steps to our backyard (and potentially pool) area. We managed to line up a few quotes which will be done in the next couple of weeks.

Our neighbour on the one side signed a fence (on top of retaining wall) height relaxation on 18/05/2013. That is really great news for us as it saves us time and money in not having to get the council to assess the requirement for the fence.

More linea on Saturday 18/05/2013.

WP_20130518_026

WP_20130518_028