I’ve been away on a couple of trips and have not had a chance to post an update.
A lot has happened in the past 3 weeks.
Plumbing was started on Saturday 04/05/2013.
Roofing was done in the week starting 06/05/2013. The roof colour is the same as the fascia and guttering i.e. colorbond surfmist. We chose a modern sloping surface (skillion) for our roof. The reason for going all surfmist for the colour is three-fold 1. helps to blend the roof into the environment, 2. better energy rating and 3. adds a modern element.
Windows, stacker and bi-fold doors were also installed during the same week.
Bedroom 5, which will probably be used for either a home gym or guest bedroom – as there is an ensuite bathroom (not referring to the portaloo in the reflection) front window. This window will have brick and render around it as a feature of the facade.
Bedroom 5 side window.
Media room.
Dining room stacker door.
Alfresco stacker door.
Family room bi-fold door.
Kitchen
Laundry room sliding door.
Powder room/Ensuite 2.
Pantry window with built-in ventilation.
Master bedroom windows.
Staircase
Study
Bedroom 3
Bathroom
Air-conditioning ducting.