We’ve had lots of progress over the past 3 weeks!
The plumbing was done on 04 & 05/04/2013.
Stormwater pits.
Preparation for the slab was done on 08 & 09/04/2013.
We put coins, from all the countries that we’ve lived in, into the slab frame. The slab was poured on 10/04/2013. All corners and edges seem to be just perfect!