Monday, 20 May 2013

Drywall and more Weatherboard

Drywall installation started on 20/05/2013.

Family

WP_20130520_001

Dining

WP_20130520_015

WP_20130520_003

WP_20130520_004

Hallway

WP_20130520_006

Store room/Media Hub

WP_20130520_007

Bedroom 5

WP_20130520_008

WP_20130520_009

Saturday, 18 May 2013

Weatherboard, Brickwork, Eaves and Insulation

The brickwork started on 10/05/2013, some of the cladding, eaves and insulation was installed during the week starting 13/05/2013.

WP_20130510_003(1)

James Hardie Scyon Linea weatherboard being installed.

 WP_20130510_005(1)

WP_20130510_011(1)

WP_20130510_014(1)

Linea around dining room stacker door.

WP_20130515_004

Alfresco ceiling and eaves.

WP_20130516_001

WP_20130516_002

Eaves around the skillion roof.

WP_20130516_003

Eaves.

WP_20130516_005

WP_20130516_007

Wall insulation was installed on 17/05/2013. Dining and family.

WP_20130517_001

Media

WP_20130517_002

More linea on 17/05/2013. Alfresco area.

WP_20130517_003

Have to love the weather in Queensland.

WP_20130517_005

WP_20130517_007

We went to the outdoor living and landscape expo on 18/05/2013 to get some ideas for finishing the steps to our backyard (and potentially pool) area. We managed to line up a few quotes which will be done in the next couple of weeks.

Our neighbour on the one side signed a fence (on top of retaining wall) height relaxation on 18/05/2013. That is really great news for us as it saves us time and money in not having to get the council to assess the requirement for the fence.

More linea on Saturday 18/05/2013.

WP_20130518_026

WP_20130518_028

Friday, 17 May 2013

Roof, Plumbing, Electrical Wiring, Air-conditioning ducting, Windows and Doors.

I’ve been away on a couple of trips and have not had a chance to post an update.

A lot has happened in the past 3 weeks.

Plumbing was started on Saturday 04/05/2013.

WP_20130505_029

Roofing was done in the week starting 06/05/2013. The roof colour is the same as the fascia and guttering i.e. colorbond surfmist. We chose a modern sloping surface (skillion) for our roof. The reason for going all surfmist for the colour is three-fold 1. helps to blend the roof into the environment, 2. better energy rating and 3. adds a modern element.

WP_20130508_019

WP_20130508_020

WP_20130506_027

WP_20130508_021

Windows, stacker and bi-fold doors were also installed during the same week.

Bedroom 5, which will probably be used for either a home gym or guest bedroom – as there is an ensuite bathroom (not referring to the portaloo in the reflection) front window. This window will have brick and render around it as a feature of the facade.

WP_20130508_005

Bedroom 5 side window.

WP_20130508_006

Media room.

WP_20130508_007

WP_20130508_012

Dining room stacker door.

WP_20130508_008

Alfresco stacker door.

WP_20130508_009

Family room bi-fold door.

WP_20130508_010

Kitchen

WP_20130508_011

WP_20130508_016

Laundry room sliding door.

WP_20130508_013

Powder room/Ensuite 2.

WP_20130508_014

Pantry window with built-in ventilation.

WP_20130508_015

Master bedroom windows.

WP_20130509_005

WP_20130509_016

Staircase

WP_20130509_007

Study

WP_20130509_008

Bedroom 3

WP_20130509_010(1)

Bathroom

WP_20130509_013

Air-conditioning ducting.

WP_20130509_014

Thursday, 2 May 2013

Meetings, Fascia, Gutters and Solar Power

This week we met with the air-conditioning contractor to discuss the placement of the thermostat and outdoor unit.

We also met the alarm system contractor to decide on the placement of the motion detectors and the keypad. The television (8) and data points (3) will also likely be done by this contractor as the builders’ regular electrician is not available and the new electrician does not really do this type of work. We will most likely add foxtel cable television, 1x additional television point, and cable provisioning for a future intercom system.

And we also met the new electrician onsite to walk through and mark the location of down lights, power points, etc. The new electrician was really knowledgeable and efficient. a walkthrough to decide on electrical is highly recommended – we managed to significantly cut down on the anticipated number of required down lights.

And we also met the solar power contractor onsite to decide on the placement of the solar panels (rear, north facing roof) and inverter (wall mounted in the garage, close to the future electrical switch box). The contractor laid the cables between the inverter and panel positions on 02/05/2013.

The majority of fascia and gutters were installed on 02/05/2013.

image

image

image

image